Tasks Interim Dates*
Student Orientation 1st week of December
Allocation of projects by Advisors to Student groups 2nd-4th week of December
Enrollment of students for ELP Course in ERP 1st week of January
ELP Start Date January 16, 2018
Establishing contacts with organizations to formulate the TORs 3rd-4th week of January
Final TOR submission to Client, Advisor, ELP Coordinator for feedback 4th week of January
Interim Report Presentation (Mid review) 1st-2nd week of April
Final Report Presentation 1st-2nd week of June